Thursday, September 24, 2009

GIB

Today we got started on the Gib first we got started on the roof. For the ceiling we used 10mm standard Gib first we would put a full sized sheet up (with a screw gun) then cut the other piece. When we had a joint we would screw up battens in the ceiling battens and then put some nails under the battens to make a little gap in the joins. When we got started on the bathroom we had to use aqua line

Thursday, August 13, 2009

Weather boards

Today we could get started on the weatherboards first we had to nail them at 600mm or nail them on each stud. We then got a story rod and marked out where each stud will sit. we could then start putting them up we would cut them to the distance and then nail gun them up in the right place. If they had to be fixed next to a window or the end of the wall we would have to pre drill a hole and then nail in a flat head 3 inch nail so it was fixed in the appropriate place.

Thursday, August 6, 2009

Soffits

Today we got started on the soffits but first we had to put 50 mm of building paper around the top of the house. We wacked up the ribbon boards and soffit bearers we had to make the ribbon board flush with the little groove in the drain where the hardys sheet sat in and then put the bearers things up.

when we put up the hardys sheet/soffits we would start on one side and put a full sheet up then cut down the other piece we needed. While we were putting them up we would have to be careful not to chip or brake them. I lernt to put them in the gutter/fasica groove first then slide them along to the joins. We would nail them 30o (mm) centers and leave a 20mm overhang on each fineshing end.

Thursday, July 2, 2009

Putting up trusses and roofing

Today we started on setting up the trusses. First we put the two inside ones up first with a brace to hold them in place. We then put a string line from one to the other to show us where to put each truss. We then nailed up each truss and then put the two outside ones up we then nailed the outrigger in the first truss and then the flyrafter to the outside of the outriggers. Then in each corner we put in a angled outrigger for strength.

We also had to nail up a brace to each truss. Once we got trusses out of the way we got started on the ceiling battarns and the purlins. While we were nailing up the ceiling battarns we had to join them on a different truss each time. We had to do the same sort of thing with the purlins. When the purlins were all nailed up we put a wiredog up in each truss.

Wednesday, June 3, 2009

Setting out and making/setting up frames




Today we got starting on the framing. We started out by using the chalk line to mark where all the walls where going to be in the house. After that we made our plates for each wall we made them them by nailing two pieces of four by two together at the right length.



We then got into setting out where our studs, windows and doors etc and this was making an allowance for corner studs, windows and so on we then went into the classroom and started writing out a cutting list. The cutting list showed use all the measurements needed for studs, window studs, bottom and top jacks, lintels and bottom trims.



Once we finished the cutting list we went outside and started making the frames. We by nailing the stud to the top and bottom jack on the points the were marked out. We then added in the the window studs the lintel and dwangs.



Once we finished smacking the frames together we started setting them up. First we got them up on the floor and made sure they were in line with our old chalk line. We then either nailed them into the other other studs, floor and braced them etc and made them square if they weren't. We would nail a brace at the top of the frame and level get a level on the side while someone pushes the way it needed to go. then we finished up by nailing the rest up and make sure they were all plumb.

We then nail on these metal straps from the floor to the frame they provided more support and strength. It was now time to get ready to start planning out the trusses but first we had to nail up to ceiling battens. We had to nail them all around the outside of the house first and make them flush with the outside of the frame the ones that where in the inside of the house we nailed them in with 50mm hanging out of each side of the frame.


Thursday, May 28, 2009

Underfloor insulation and Floor boards


Today we started nailing in the floor boards. But first we had to cover the whole house with the thermal silver paper to keep the warmness inside the house when its built.


After that we got started on the floor. We set up string lines from one end of the house to the other (length) to show us where we cut threw the underfloor silver paper for the glue to stick to the floor boards.


we then took the string lines down and started on the floor. At first we had someone gluing each hole and two other people would lay down the boards. Once it was laid down we had to give it a whack where it needed to be tight and flash.
Our flooring sheets were all staggered as per normal installation meaning the first row started with a full sheet and then the next started with half a sheet. During this exercise i learnt completely how to put floor boards down as id never done it before.

Wednesday, May 27, 2009

Ramset gun licence

Today i passed a written test about safety in the work site using a ramset gun. Then we went out side and learnt how to loaded, reload and unload the nails (safety) and we had a shot on each gun (three in total)